The steam piping system is an essential part of steam power plant. The piping steam used for carrying the steam must fulfill the following requirements:

1. The piping adopted must ensure maximum reliability.

2. It should be possible to carry out inspection and maintenance on any section of the plant without the need for complete shut down

3. The piping should be of necessary size to carry the required flow of fluids

4. The pipes carrying the fluids at high temperature should be able to withstand the temperature and expansion caused due to the temperature changes.

5. The piping supports, anchors, and joints should be in accessible positions so that inspection is possible throughout the life of the plant.

6. The piping system must withstand the pressure to which it is subjected.

7. The pipe should run as direct and straight as possible. The number of fittings and bends required to make the necessary connections should be as minimum as possible to reduce the pressure loss. This is also desirable for easy inspection and maintenance.

8. Valves and interconnecting pipes should be as few as possible, but the necessity for sectionalising and load transfer in times of emergency, inspection or maintenance should not be overlooked

9. Consideration should be given to the efficient drainage of all pipes although the number of drainage points should be as few as possible consistent with safety

10.The pipes should be made in the longest possible lengths to reduce the number of joints

11. Template pipes should be as few as possible, to reduce erection time.

12. The piping system, used for steam, should be installed in Such a way that the horizontal runs should slope in the direction of steam flow. The steam traps along the piping should be provided to drain the line and to prevent an accumulation of water during steam flow.

With advancing temperature and pressures and with the increasing complexity of the central station cycle in modern power plants, the cost of piping system has become one of the major items of expense and its selection and arrangement has also become one of the major items of design